Unlocking the True Value of Your Power Plant with TCR's Life Extension Studies - The India and Saudi Arabia Playbook

  • Writer: Rohit Bafna
    Rohit Bafna
  • 11 minutes ago
  • 16 min read

Here's the conversation I had last month with the CEO of a 500MW thermal plant in Gujarat.


"We've been told our boiler tubes need complete replacement. Cost: ₹450 crores. Timeline: 18-month shutdown."


I asked one question: "When was the last time someone actually measured remaining life based on real operating data?"


Silence.


That's exactly why TCR's power plant life extension studies exist.

Because in India and Saudi Arabia's rapidly expanding power markets, the difference between data-driven decisions and educated guesses is measured in hundreds of crores.


The Reality Facing Power Plants in India and Saudi Arabia Right Now

Let me give you the numbers that should keep every plant manager awake at night.

India's power demand is projected to more than double by 2035. That's not growth. That's a tsunami.


Meanwhile:

  • Your existing thermal plants are aging

  • Coal quality keeps fluctuating

  • Environmental regulations are tightening

  • Renewable integration is creating operational challenges

  • Capital for new plants is scarce


In Saudi Arabia, the situation is different but equally challenging:

  • Vision 2030 pushing aggressive renewable targets

  • Existing gas-fired plants need to remain backbone of grid stability

  • Extreme operating temperatures accelerating equipment degradation

  • Water-cooled systems facing stress from water scarcity


The question isn't whether to extend plant life. The question is how to do it without gambling ₹500 crores on guesswork.


What Most Power Plants Get Wrong About Life Extension

I've reviewed 47 life extension studies from various consultants over the past three years.


Here's what 80% of them have in common:

  • Generic recommendations copied from textbooks

  • Conservative assumptions that overstate replacement needs

  • No correlation between actual operating conditions and remaining life

  • Failure to account for plant-specific operating history

The result? Plants either spend crores unnecessarily or ignore critical issues until catastrophic failure forces unplanned shutdowns.

Real example from Rajasthan: 210MW unit recommended for ₹280 crore boiler overhaul. Our actual assessment using non-destructive testing and metallurgical analysis: Only 15% of tubes needed replacement. Actual cost: ₹42 crores. Savings: ₹238 crores.

That's not optimisation. That's business transformation.


TCR's Approach to Power Plant Life Extension Studies


We Start with Economics, Not Engineering

Most consultants start by telling you what's wrong with your plant.

We start by asking: What's the business case for keeping this plant running?


Our cost-benefit framework considers:

  • Market power prices: What's the forward curve telling us?

  • Capacity utilisation: How many hours annually will this plant actually run?

  • Fuel costs: Coal price trends, gas availability, transportation logistics

  • Environmental compliance costs: What's coming in the regulatory pipeline?

  • Alternative options: What does new capacity or plant retirement actually cost?


Only after establishing economic value do we dive into technical assessment.

Because there's no point in extending the life of a plant that shouldn't be running in the first place.


While Your Plant Keeps Running

Traditional life extension studies require shutdowns. That's 30-90 days of lost generation. At ₹3-4 per unit, that's real money.


TCR's methodology allows assessment during normal operations:

  • Online inspection techniques: Using advanced NDT methods that don't require equipment isolation

  • Remote monitoring: Continuous data collection without operational interference

  • Planned outage optimisation: Coordinating necessary inspections with scheduled maintenance

  • Predictive analytics: Trending operational parameters to forecast remaining life


Recent GCC project: Three 400MW combined cycle units. Full life extension study completed with zero unplanned downtime. Used annual maintenance windows for critical inspections. Result: Operational continuity maintained while gathering comprehensive data.


The Technical Foundation: What We Actually Measure


Critical Pressure Parts Assessment


Boiler tubes - the heart of thermal plants:

What most consultants do: Visual inspection and maybe some thickness readings.

What TCR does:

  • Metallographic replica testing: Understanding microstructural degradation without removing material

  • Advanced ultrasonic testing: Mapping wall thickness variations across entire tube banks

  • Oxide scale analysis: Quantifying fireside and waterside corrosion rates

  • Creep damage assessment: Actual cavity counting per ASTM E139 standards

  • Remaining life calculations: Based on real operating temperatures and stresses, not nameplate values


For Saudi plants specifically: High ambient temperatures push cycle efficiency down. Operators compensate by running hotter steam temperatures. This accelerates creep damage in superheater and reheater tubes.


Our assessment methodology per ASME PCC-3: Correlates actual steam temperature data with material-specific Larson-Miller parameters. Provides remaining life estimates with statistical confidence intervals. Not "probably good for 5 more years" but "87% probability of 8+ years at current operating conditions."


Turbine Life Assessment


High-pressure, intermediate-pressure, and low-pressure rotors:

Critical failure modes we assess:

  • Low-cycle fatigue: Start-stop cycles causing cumulative damage

  • Creep deformation: High-temperature sections experiencing time-dependent strain

  • Stress corrosion cracking: Especially in LP turbines with wet steam conditions

  • Erosion damage: Particularly relevant for Indian plants burning high-ash coal


  • Bore sonic inspection: Detecting internal cracking in rotors

  • Blade vibration analysis: Understanding high-cycle fatigue risk

  • Material sampling and testing: Verifying mechanical properties haven't degraded

  • Residual life calculations: Per API 579 fitness-for-service methodology


India-specific challenge: Frequent load cycling due to renewable integration. Turbines designed for baseload now operating in cycling mode. This fundamentally changes fatigue damage accumulation.


Our approach: Actual operational data from DCS/historian systems. Rainflow counting analysis of thermal cycles. Damage fraction calculations per ASME FFS-1.


Balance of Plant Assessment


Equipment that's often overlooked but critical:


Heat exchangers and condensers:

  • Tube bundle integrity assessment

  • Fouling impact on thermal performance

  • Remaining life vs. replacement economics


Piping systems:

  • High-energy piping inspection per ASME B31.1

  • Flow-accelerated corrosion in feedwater systems

  • Thermal fatigue in two-phase flow regions


Auxiliary systems:

  • Boiler feed pumps and performance trending

  • Forced draft and induced draft fans

  • Coal handling plant equipment condition


The India-Specific Context: What Makes Our Market Unique


Coal Quality Variability

The challenge nobody talks about: Indian power plants rarely burn the coal they were designed for.

Design coal: 4000-4500 kcal/kg Actual coal: Anywhere from 2800-5200 kcal/kg depending on linkage, imports, and e-auction purchases

Consequences for equipment life:

  • High ash: Accelerated erosion in mills, burners, and convective sections

  • High moisture: Reduced combustion efficiency and mill capacity

  • Variable sulfur: Fluctuating dew point temperatures affecting cold-end corrosion

  • Chlorine content: Enhanced high-temperature corrosion in superheaters

Our assessment methodology: Correlates actual coal quality data (not design values) with observed equipment degradation. This gives realistic remaining life projections based on what you're actually burning.


Case study - 2x250MW plant in Chhattisgarh: Burning 30% imported Indonesian coal blended with domestic coal. Consultant's generic study: "Superheater tubes need replacement within 2 years." Our analysis: High-ash Indonesian coal causing different failure mechanisms. Recommendation: Modified sootblowing frequency and selective tube replacement. Result: 7 additional years of operation vs. complete replacement. Savings: ₹180 crores.


Environmental Compliance Driving Retrofits

Post-2015 emission norms forcing major capital expenditure:

FGD installation: ₹100-150 crores for 500MW unit ESP upgrades: ₹40-60 crores NOx control: ₹50-80 crores for SCR systems

The critical question: Does it make sense to invest ₹300 crores in emission control for a plant with 5 years of economic life?

Our integrated analysis:

  • Remaining technical life of critical equipment

  • Projected capacity utilisation factor under merit order dispatch

  • Power purchase agreement terms and remaining tenure

  • Regulatory timeline for emission compliance

  • Alternative options including retirement and replacement


Recent engagement with 4x210MW station in Maharashtra: Total emission control investment: ₹850 crores. Our life extension study showed economic viability for only 2 out of 4 units. Recommendation: Retrofit 2 units, retire 2 units, invest savings in 500MW supercritical unit. NPV improvement: ₹420 crores vs. original plan.


Renewable Integration Challenges (And How They're Changing Everything)


India added 17 GW of solar in 2023. That's wonderful for the planet. That's creating both challenges AND opportunities across the energy sector.

What renewable integration means for thermal plants:

  • Increased cycling operation (2-3 starts per day vs. baseload)

  • More low-load operation (30-40% MCR) with associated inefficiencies

  • Rapid ramping causing thermal stresses

  • Frequent start-stop cycles accelerating fatigue damage

What renewable integration means for green energy assets:

  • Wind and solar farms aging faster than expected in Indian conditions

  • High ambient temperatures affecting solar panel degradation rates

  • Monsoon humidity impacting electrical connections and inverters

  • Dust and pollution reducing panel efficiency by 20-30% annually


Our comprehensive energy sector assessment covers:

For thermal plants:

  • Cycling damage assessment using actual operational data

  • Future cycling pattern projections based on renewable capacity additions

  • Modifications enabling flexible operation without premature failure

  • Economic impact analysis of reduced PLF on unit economics

For renewable assets:

Hybrid power plant assessment: Some of the smartest operators are building renewable-thermal hybrids. Using existing thermal plant infrastructure and grid connections. Adding solar/wind capacity in the same location.


Recent project - 660MW thermal + 200MW solar hybrid, Karnataka: Thermal plant operating at 40% PLF due to merit order displacement. Added solar capacity using existing transmission infrastructure. Our assessment: Thermal plant life extension focused on peaking duty capability. Result: Combined facility economics dramatically improved vs. thermal-only operation.


The Saudi Arabia Context: Desert Operations and Grid Stability

Extreme Operating Environments

Ambient conditions that stress equipment design limits:

Summer temperatures routinely exceeding 50°C:

  • Gas turbine derating of 15-20% during peak demand periods

  • Cooling system performance degradation

  • Auxiliary equipment failures from heat exposure

Sand and dust ingress:

  • Compressor blade erosion

  • Filter system loading

  • Cooling tower fill fouling

Water scarcity:

  • Dry cooling system constraints

  • Water treatment challenges

  • Scaling and fouling in heat exchangers

Our assessment methodology for Gulf region plants:

  • Actual ambient temperature trending and impact on equipment

  • Corrosion assessment specific to coastal environments

  • Materials degradation from desert operating conditions

  • Cooling system performance optimization studies


Vision 2030 and the Baseload Stability Question


Saudi Arabia targeting:

  • 50% renewable energy by 2030

  • 58.7 GW total installed capacity

  • Continued economic growth driving 5-6% annual demand increase


The paradox: More renewables require more flexible baseload capacity for grid stability.


What this means for existing plants: Your gas-fired combined cycle units become MORE valuable, not less. But they need to operate differently than designed.


Life extension studies must address:

  • Cycling capability and remaining fatigue life

  • Fast-start capability modifications

  • Part-load efficiency improvements

  • Grid ancillary services provision


Recent project - 2x400MW CCGT in Eastern Province: Original design: Baseload operation at 85%+ PLF Current reality: Cycling operation with 65% PLF Our study evaluated:

  • Hot start capability improvements

  • Turbine blade cooling modifications

  • Heat recovery steam generator fatigue life

  • Economic viability of continued operation vs. new flexible capacity


Result: 12-year life extension with ₹2.1 billion investment Alternative: New 800MW plant at ₹4.8 billion NPV advantage: ₹1.3 billion over 12-year period


The TCR Methodology: How We Actually Deliver Value


Phase 1: Data Gathering and Economic Framing (Weeks 1-2)

Documents we review:

  • Original design documentation and P&IDs

  • Operating and maintenance history (minimum 5 years)

  • DCS/historian data for critical parameters

  • Previous inspection reports and outage records

  • Fuel quality records and water chemistry data

  • Financial performance and power dispatch data

Stakeholder interviews:

  • Plant managers on operational challenges

  • O&M teams on recurring issues

  • Finance teams on economic constraints

  • Corporate strategy on portfolio plans

Economic modeling:

  • Forward power price curves

  • Fuel cost projections

  • Capacity utilisation forecasting

  • Regulatory compliance requirements

  • Alternative investment options

Deliverable: Executive brief outlining business case for life extension


Phase 2: Non-Intrusive Assessment (Weeks 3-6)

While plant operates normally:

Remote monitoring and data analysis:

  • Thermal performance trending

  • Vibration analysis for rotating equipment

  • Efficiency deterioration patterns

  • Operational anomalies identification

Online inspection techniques:

  • Rope access boiler tube inspection

  • Infrared thermography for refractory condition

  • Acoustic emission testing for crack detection

  • Partial discharge testing for electrical equipment

Laboratory testing of representative samples:

Deliverable: Preliminary technical assessment identifying areas requiring detailed inspection


Phase 3: Detailed Inspection During Planned Outage (Weeks 7-10)

Coordinated with annual maintenance shutdown:

Comprehensive NDT coverage:

Invasive inspection where necessary:

  • Turbine internal inspection and measurements

  • Boiler internal condition assessment

  • Pressure part sample extraction for laboratory analysis

  • Refractory thickness gauging

Advanced diagnostic testing:

  • Vibration signature analysis

  • Oil analysis for bearing condition

  • Thermographic surveys

  • Performance testing at multiple loads

Deliverable: Comprehensive technical condition assessment with remaining life calculations


Phase 4: Cost-Benefit Analysis and Recommendations (Weeks 11-12)

Integration of technical findings with economic framework:

Three scenarios developed:

  1. Minimal intervention: What's absolutely necessary for continued safe operation

  2. Optimal intervention: Best NPV considering remaining economic life

  3. Life extension: Maximum technical life with required investments

Each scenario includes:

  • Detailed scope of work and engineering specifications

  • Capital expenditure requirements and phasing

  • Maintenance cost implications

  • Performance improvement potential

  • Risk assessment and mitigation measures

  • Timeline and outage requirements

Sensitivity analysis:

  • Power price variations

  • Fuel cost changes

  • Capacity utilisation scenarios

  • Regulatory changes impact

Deliverable: Executive presentation with clear recommendation and implementation roadmap


Real Results from Recent Engagements


Case Study 1: 2x500MW Supercritical Unit, Uttar Pradesh

Client challenge: 10-year-old supercritical units experiencing waterwall tube failures. OEM recommending ₹380 crores for complete waterwall replacement. Management questioning economic viability.

TCR's approach:

  • Detailed failure analysis of failed tubes

  • Systematic NDT survey of entire waterwall system

  • Water chemistry audit and historical trending

  • CFD modeling of furnace heat flux patterns

Findings:

  • Failures concentrated in specific zones due to localized overheating

  • Root cause: Coal fineness outside design specification causing flame impingement

  • 85% of waterwall tubes in good condition

  • Water chemistry within acceptable range

Recommendations:

  • Selective tube replacement in affected zones: ₹45 crores

  • Mill performance improvement: ₹12 crores

  • Enhanced monitoring system: ₹3 crores

  • Revised operating procedures: No cost

Total investment: ₹60 crores Avoided cost: ₹320 crores Additional benefit: Root cause elimination prevents recurrence

Plant manager's feedback: "TCR saved us from a decision that would have destroyed our unit economics. The OEM was recommending complete replacement because that's what they sell. TCR told us what we actually needed."


Case Study 2: 6x660MW Supercritical Station, Gujarat

Client challenge: Preparing for major overhaul of all six units. Internal estimates: ₹2400 crores over 5 years. Board questioning return on investment given renewable capacity additions.

TCR's approach:

  • Comprehensive life extension study across all six units

  • Individual unit economic modeling based on age, condition, and performance

  • Portfolio optimisation considering state power demand and renewable integration

  • Scenario planning for emission compliance timeline

Findings:

  • Units 1&2 (oldest): Limited remaining economic life due to poor heat rate

  • Units 3&4 (mid-age): Strong economics with targeted improvements

  • Units 5&6 (newest): Excellent condition with 20+ year outlook

Recommendations:

  • Units 1&2: Minimal maintenance, retire after 3 years

  • Units 3&4: ₹180 crores investment for 15-year life extension

  • Units 5&6: ₹80 crores for efficiency improvements

  • Total investment: ₹260 crores vs. ₹2400 crores original plan

NPV improvement: ₹1850 crores

CFO's response: "This changed our entire capital allocation strategy. We're now investing the savings in a new 800MW supercritical unit with better economics than trying to fix what shouldn't be fixed."


Case Study 3: 4x375MW CCGT Station, Saudi Arabia (Riyadh Region)

Client challenge: 20-year-old combined cycle units facing increasing maintenance costs. GT compressor performance degradation from sand erosion. HRSG tube leaks becoming more frequent. Management considering complete plant replacement.

TCR's approach:

  • Gas turbine hot gas path inspection and remaining life assessment

  • HRSG tube condition survey using advanced NDT

  • Compressor blade erosion quantification

  • Economic modeling of continued operation vs. new plant

Findings:

  • GT hot section components at 60% of design life

  • HRSG tube failures due to thermal fatigue, not end-of-life

  • Compressor erosion manageable with coating technology

  • Plant economics remain strong due to gas availability

Recommendations:

  • GT compressor blade coating: $18 million

  • HRSG selective tube replacement: $24 million

  • Advanced monitoring systems: $6 million

  • Operating procedure optimisation: Minimal cost

  • Total investment: $48 million for 10-year life extension

Alternative: New 1500MW CCGT plant at $850 million

Financial outcome: Life extension IRR: 34% New plant IRR: 18% Clear winner: Life extension

Plant director's comment: "TCR's analysis gave us confidence to commit capital to existing assets rather than chasing new capacity. The Board approved immediately when they saw the economics."


Standards and Methodologies We Follow

Because "trust me" isn't a technical specification:


International Codes and Standards

ASME Boiler and Pressure Vessel Code:

  • Section I: Power Boilers

  • Section II: Materials specifications

  • Section V: Non-destructive examination

  • Section IX: Welding qualifications

API Standards:

  • API 579-1/ASME FFS-1: Fitness-For-Service

  • API 571: Damage Mechanisms Affecting Fixed Equipment

  • API 580: Risk-Based Inspection

ASTM Standards:

  • ASTM E139: Conducting Creep, Creep-Rupture, and Stress-Rupture Tests

  • ASTM E1820: Measurement of Fracture Toughness

  • ASTM A262: Detecting Susceptibility to Intergranular Attack

EPRI Guidelines:

  • Boiler Tube Failure Metallurgical Guide

  • Fossil Plant High Energy Piping Damage

  • Turbine-Generator Auxiliary Systems Maintenance Guides


India-Specific Regulations

CEA (Central Electricity Authority) Regulations:

  • Technical Standards for Construction of Electrical Plants

  • Safety Requirements for Thermal Power Stations

  • Grid Connectivity Standards

MoEF&CC (Ministry of Environment) Norms:

  • Emission standards for thermal power plants

  • Water consumption and discharge requirements

  • Ash utilisation mandates

Indian Standards (BIS):

  • IS 2062: Steel for General Structural Purposes

  • IS 3601: Code of Practice for Welding of Carbon Steel Pressure Vessels

  • IS 10392: Thermal Power Station Design and Operation


Common Questions About Power Plant Life Extension


How long does a complete life extension study actually take?

Realistic timeline: 3-4 months

Breakdown:

  • Data collection and economic framing: 2-3 weeks

  • Online assessment while operating: 3-4 weeks

  • Detailed inspection during outage: 2-3 weeks

  • Analysis and reporting: 3-4 weeks

Critical path item: Coordinating detailed inspection with planned outage.

We can accelerate: If management needs quick decisions, we can provide preliminary assessment in 6 weeks. But comprehensive study requires full inspection cycle.


What if our plant doesn't have good historical operating data?

Reality check: Most Indian plants have incomplete records.

Our approach when data is limited:

  • Focus on physical condition assessment vs. trending analysis

  • Use industry benchmarks for similar units

  • Conduct accelerated monitoring campaign (3-6 months)

  • Conservative assumptions in remaining life calculations

Bottom line: Lack of historical data increases uncertainty but doesn't prevent assessment.

We just need to be transparent about confidence levels in our conclusions.


Can you guarantee the remaining life estimates?

Let me be brutally honest: No one can guarantee remaining life.

What we provide:

  • Statistical confidence intervals based on measured data

  • Sensitivity to key operating parameters

  • Comparison with industry experience

  • Clear statement of assumptions and limitations

Example statement from our reports: "Based on measured creep damage and projected operating conditions, this superheater section has a remaining life of 8-12 years with 80% confidence, assuming continued operation within design parameters."

That's not a guarantee. That's an engineering assessment with quantified uncertainty.

Anyone offering guarantees is either lying or not understanding the physics.


What's the typical ROI on life extension investments?

Depends entirely on your specific situation.

But here are typical ranges we see:

High-performing plants in good markets:

  • IRR: 25-40%

  • Payback: 2-4 years

  • Strong case for life extension

Average plants in competitive markets:

  • IRR: 15-25%

  • Payback: 4-6 years

  • Life extension usually makes sense

Poor performers or stranded assets:

  • IRR: Below 15%

  • Payback: 7+ years

  • Retirement often better option

Key insight: Life extension isn't always the right answer. Sometimes the best recommendation is planned retirement and reallocation of capital.


How do you handle conflicting interests between operations and finance teams?

This is where the rubber meets the road.

Operations team typically wants:

  • Maximum reliability

  • Zero risk tolerance

  • Gold-plated solutions

  • "Do it right" mentality

Finance team typically wants:

  • Minimum investment

  • Maximum returns

  • Risk acceptance

  • "Do it cheap" mentality

Our role as honest broker: Present multiple scenarios with clear trade-offs. Show economic impact of different risk tolerance levels. Facilitate decision-making based on facts, not opinions.

Example from recent project: Operations wanted ₹180 crores for complete HP turbine rotor replacement. Finance wanted ₹20 crores for basic maintenance only.

TCR's analysis showed:

  • ₹85 crores for selective blade replacement plus modified operating envelope

  • Achieves 90% of desired reliability improvement

  • IRR of 28% vs. 12% for complete replacement

Result: Both teams aligned on middle path that optimised economics and reliability.


The Future of Power Generation in India and Saudi Arabia

India: Doubling Down on Capacity While Going Green

The paradox we're navigating: Power demand doubling by 2035. Renewables growing from 34% to 55% of generation.

What this means for thermal plants:

  • Fewer will run, but those that do become MORE valuable for grid stability

  • Cycling operation becomes the norm, not baseload

  • Flexibility and fast-start capability premium over pure efficiency

  • Life extension decisions must account for changing dispatch patterns

But here's the green energy reality: Solar and wind are intermittent. Data centres need 24/7 power. Electric vehicle charging creates new demand peaks.

The grid needs BOTH:

  • Clean baseload from nuclear and hydro

  • Flexible thermal capacity for stability

  • Massive renewable capacity for emissions reduction

  • Battery storage for intraday balancing

TCR's role spans the entire energy mix: Helping thermal operators understand which assets to bet on. But also supporting renewable asset owners with critical inspection services.


Our renewable energy services:

Recent wind energy project - Rajasthan: 100 wind turbines, 10+ years old, experiencing foundation cracking. Our assessment: Combination of fatigue loading and soil settlement. Solution: Selective strengthening vs. complete replacement. Savings: ₹45 crores while extending farm life by 15 years.


Saudi Arabia: Balancing Baseload Stability with Renewable Ambitions


Vision 2030 creating opportunities: Massive renewable deployment requires flexible backup capacity. Existing gas-fired plants perfectly positioned IF properly maintained.


But Saudi Arabia is also building the world's largest green hydrogen facility. NEOM project targeting 4 GW of renewable power for hydrogen production.


What this means: The kingdom needs thermal plants for grid stability AND renewable infrastructure for decarbonisation.


The water-energy nexus: Desalination driving significant electricity demand. Co-located power and water plants need coordinated life extension strategies. Meanwhile, green hydrogen could eventually power desalination directly.


TCR's Gulf region renewable expertise:

  • Desert solar farm degradation: Sand erosion impact on panel mounting structures

  • Offshore wind foundations: Marine corrosion assessment for Red Sea projects

  • Hydrogen pipeline materials: NACE testing for hydrogen embrittlement resistance

  • Thermal storage systems: High-temperature materials evaluation


Recent Saudi renewable engagement: 300 MW solar farm experiencing premature tracker bearing failures. Our analysis: Combination of thermal cycling and dust infiltration. Recommendation: Modified sealing systems and material upgrades. Result: Reduced maintenance costs by 40% and improved energy yield.


Why TCR Engineering for Power Plant Life Extension

50 Years of Materials and Inspection Expertise

We're not management consultants dabbling in power. We're materials scientists and engineers who've been testing power plant components since 1973.

Our foundation:

What this means for you: When we say a tube has 5 years of remaining life, it's based on actual metallurgical testing, not educated guesses.


Global Experience, Local Understanding

International projects:

  • Middle East power plants: 15+ life extension studies

  • Indian thermal sector: 30+ comprehensive assessments

  • Southeast Asia: Combined cycle and coal-fired units

We understand:

  • Indian coal quality variations and impact on equipment

  • Gulf region environmental challenges

  • Regulatory landscapes in both markets

  • Local contractor capabilities and limitations


Complete Technical Capabilities Under One Roof

Unlike consulting firms that subcontract testing:

Our in-house capabilities span conventional AND renewable energy:

For thermal and CCGT plants:

For renewable energy infrastructure:

  • Wind turbine structural inspection and blade analysis

  • Solar panel degradation and efficiency testing

  • Battery storage thermal management assessment

  • Green hydrogen material compatibility testing

  • Composite materials testing for wind blades

For hybrid and energy storage systems:

  • Grid integration equipment testing

  • Power electronics reliability assessment

  • Energy storage containment integrity

  • Thermal cycling and safety testing

Advantages:

  • Faster turnaround (no coordination with third parties)

  • Better quality control across diverse technologies

  • Lower overall cost through integrated approach

  • Single point of accountability for entire energy portfolio


Getting Started with Your Life Extension Study

What We Need from You

To provide accurate proposal and timeline:

Plant information:

  • Capacity, configuration, and vintage

  • OEM and major equipment suppliers

  • Recent performance parameters (heat rate, availability)

  • Known problem areas or concerns

Operating data (if available):

  • Last 3-5 years of DCS/historian data

  • Outage history and major repairs

  • Current maintenance budgets

  • Fuel quality records

Business context:

  • Power purchase agreements and remaining tenure

  • Corporate strategy for this asset

  • Regulatory compliance requirements

  • Capital budget constraints

Decision timeline:

  • When do you need recommendations?

  • When is next major outage?

  • What's driving the urgency?

Investment Range Expectations

Study costs typically:

  • Single unit basic assessment: ₹25-40 lakhs

  • Comprehensive multi-unit study: ₹80 lakhs - 1.5 crores

  • Depends on plant size, complexity, and scope

Implementation costs vary widely:

  • Minimal intervention: ₹20-50 crores

  • Moderate life extension: ₹100-200 crores

  • Comprehensive overhaul: ₹300-500 crores

Our goal: Optimise total lifecycle costs, not just study fees.

Timeline to Decision

Typical engagement:

  • Initial discussion and proposal: 1 week

  • Study execution: 3-4 months

  • Management presentation: 1-2 weeks

  • Board approval: Client timeline

  • Implementation planning: 2-4 weeks

Fast-track option: If decision urgency requires, we can provide preliminary assessment in 6 weeks. Final recommendations follow after detailed outage inspection.

The Bottom Line on Power Plant Life Extension

Your power plant is either worth extending or it's not.

That decision should be based on:

  • Actual equipment condition, not age

  • Real market economics, not sunk cost fallacy

  • Future operating requirements, not past performance

  • Data-driven analysis, not consultant opinions

TCR's power plant life extension studies provide exactly that.

We've helped operators in India and Saudi Arabia make informed decisions on ₹5000+ crores of potential investments.

Sometimes we recommend aggressive life extension. Sometimes we recommend planned retirement. Always we recommend what the data says, not what anyone wants to hear.


Ready to understand what your plant is really worth?

Contact TCR Engineering:

  • Call: +91 9833530200

  • Email: sales@tcreng.com

  • Visit: Our Mumbai laboratory and discuss your specific situation


We'll review your plant information and provide a detailed proposal within one week.


No hidden costs. No predetermined conclusions. Just honest technical and economic analysis that helps you make the right decision for your business.


Because in a power market where India's demand is doubling and Saudi Arabia is transforming its energy mix, the plants that win are the ones making decisions based on data, not hope.


That's where TCR's power plant life extension studies turn uncertainty into competitive advantage.