Failure Analysis project from Adani Power Plant

2014-07-08 · 1 min read · By TCR Newsroom

Adani Power service order of 2014 to TCR Advanced Engineering for boiler tube failure analysis at Tiroda, with order numbers and contact details removed

Article

In June 2014, Adani Power issued TCR Advanced Engineering, the TCR group company in Vadodara, Gujarat, India, a service order for boiler tube failure analysis on an as and when required basis at the 5 x 660 MW Tiroda Thermal Power Plant in Gondia district, Maharashtra.

  • Client: Adani Power, Tiroda Thermal Power Plant
  • Plant: 5 x 660 MW, Tiroda, Gondia district, Maharashtra
  • Service: boiler tube failure analysis, as and when required
  • Service order: June 2014
  • Industry: power generation

TCR Advanced has received an order from Adani Power to provide boiler tube failure analysis on an as and when required basis for the 5 x 660 MW Tiroda Thermal Power Plant at Tiroda village, Gondia district, Maharashtra.

Adani Power service order of 2014 to TCR Advanced Engineering for boiler tube failure analysis at Tiroda, with order numbers and contact details removed
Adani Power service order of 2014 to TCR Advanced Engineering for boiler tube failure analysis at Tiroda, with order numbers and contact details removed

FAQ

What did the Adani Power service order at Tiroda cover?

The service order, placed in June 2014, engaged TCR Advanced Engineering to carry out boiler tube failure analysis on an as and when required basis for the 5 x 660 MW Tiroda Thermal Power Plant in Gondia district, Maharashtra. Each analysis establishes the damage mechanism behind a failure and the corrective action against a recurrence.

What other work has the TCR group done at Tiroda?

From June 2025, the group's work at Adani Power Tiroda includes remaining life assessment of the boiler and critical piping for Units 1, 3 and 4, and remaining life assessment of the turbine generator. Remaining life assessment in the TCR group is delivered and signed by TCR Advanced Engineering, with test inputs from TCR Engineering.

Which TCR company received the Tiroda failure analysis order?

The order was placed with TCR Advanced Engineering Pvt. Ltd., the TCR group company in Vadodara, Gujarat, whose Managing Director, Paresh Haribhakti, co-authored the ASM International book Failure Investigation of Boiler Tubes: A Comprehensive Approach. TCR Advanced is a group company of TCR Engineering under common promoters, not a subsidiary.